The system includes the following surface objects:
• 7 Compressor Stations,
• 4 Metering Stations,
• 12 Pigging Stations,
• 49 Block Valve Stations,
• 2 Off-take Stations to supply Türkiye’s domestic natural gas network.
At present, TANAP has two compressor stations, one in the Damal area of Ardahan and the other in the Seyidgazi area of Eskisehir. The number of compressor stations will be 7 when TANAP’s capacity is projected to reach a maximum design capacity of 31 bn m3.
TANAP in figures
• The total length is 1,850 km
• More than 30% of the pipeline was built 2,000 meters above sea level
• A total of 131,620 steel pipes (circa 1.3 million tonnes), each with an average length of 13 metres
• 100,000,000 people/hour
• The highest point through which the pipeline passed was 2,760 m, and the deepest point was 65 metres below sea level,
• As part of the construction work, 13,000,000 m of excavation work and about 7,000 special crossings were built,
• Commercial gas flow at TANAP, which employed 13,000 people during the peak period of the project, started on the 30 June 2018,
• Carried out 1,000 projects to accelerate socio-economic development and protect nature in districts, towns and villages along the TANAP route through the Social and Environmental Investment Programme (SEIP), one of the largest private and environmental investment programmes implemented by the private sector in Türkiye.